Pos.

Activity

Time

Date(s)

Duration

1

 

Deployment test

09.07.1999

-

2

Vibration test

13.-15.07.1999

3 days

3

Deployment test

16.07.1999

-

4

TV test

19.-27.07.1999

10 days

5

Deployment test

03.08.1999

-

6

Properties

05.08.1999

1 day

7

Deployment test

09.08.1999

-

8

Modification

2 days

9

Deployment test

-

10

Centrifuge test

1 day

11

Deployment test

-

12

Delivered to Alenia

13.09.1999

13

Incoming inspection (Alenia)

13.-14.9.1999